Uttara Residential Model Town (3rd phase)
Present Position of the Project :
Site development: Site development work already completed about 92% and remaining work is in progress.

Road Construction: Road Construction work already completed about 70% and remaining work is in progress. It is mentioned here that 02 nos group of road work are stopped due to ahead construction of Uttara Apartment Project at Sector -18.

Bridge Work: Amongst 11 nos bridges have been already completed. 07 Nos bridges are running, 01 no bridge is in under approval and tender is invited fro remaining 01(one) Bridge.

Lake Development and Protection: Amongst 12 Nos lakes, 10 nos lakes are running and contract of remaining 02 nos lakes have been cancelled and tendering of remaining 02 (two) lakes is under process.
 
Utility services:
Electricity: Dhaka Electricity Supply Co. (DESCO) is doing the electrification work of the project area as deposit work. Electric poles are already partially installed in all sectors. DESCO authority will take necessary action to connect & supply of electricity as ver allotee's demand..

Water Supply: Dhaka WASA will execute the work as deposit work and construction of deep tube well and pipe line network will start soon.

Gas Supply: Gas line installation work will be executed with the consultation with TITAS Gas Co. But still the consent of execution is not yet received from TITAS Gas Co.

Plot Handing Over: About 4000 residential plots have been already handed over to the respective allottees, Remaining will be handed over gradually at the earliest possible time.

Project completion: Target has been already fixed to complete project in all aspect by December 2016.